Detection and Alarm
2. The Contractor shall provide staff to test all devices and all operational
features of the System for witness by the Owner’s representative and the
Authority having jurisdiction. The Contractor shall provide two-way radio
communications to assist in the testing. All testing must be witnessed by
the owner’s representative, prior to acceptance.
3. The testing and certification shall take place as follows:
a. System shall be tested in conjunction with the manufacturer’s
representative.
b. All deficiencies noted in the above test shall be corrected.
c. Test results shall be submitted to the consultant or owner’s
representative.
d. System test witnessed by owner’s representative and correction of
any deficiencies noted.
e. The owner’s representative shall accept the System.
f. System test shall be witnessed by the Authority having
Jurisdiction, and any deficiencies that are noted shall be corrected.
4. A letter of certification shall be provided to indicate that the tests have
been performed and all devices are operational.
END OF SECTION